STATUS OF BHARATNET AS ON 17.06.2018

 

 

S.N.

Description of Work

Status

1.

OFC Pipe laid

2,75,367 Kms (1,19,247 GPs)

2.

Optical Fibre laid

2,80,767 Kms (1,17,016 GPs)

3.

Tenders Finalized

3291 Blocks / 1,22,828 GPs

4.

Work Started*

3281 Blocks / 1,22,121 GPs

5.

Current Weekly performance of Optical Fibre laying

2057Kms

6.

Current Weekly performance of OFC Pipe laying

1674Kms

7.

Optical Fibre Cable Delivered on site 

3,38,264 Kms

8.

Service Ready GPs

1,11,510 GPs

* does not include the data of Andhra Pradesh 